DIY Gantry Crane – Height Adjustment

Introduction

Do You Need To Change Height?

Common Lifting Mechanisms for Gantry Cranes

Design Goals

The Synchronization Problem

This image shows the final check of alignment after the winch brackets were installed. The two posts are closer together than they would be normally because the top beam had yet to be installed.
Figure SP-2-1: Final check of alignment after installing the winch brackets.

Hardware Modifications

This image shows the winch selector mechanism engaged with the teeth of the spur gear. It was important for the two selectors to function identically even though they mirrored each other.
Figure SP-2-2: The winch selector mechanism engaged with the spur gear.

Bushing Modifications

This image shows the bushing on the cranking shaft, which allows the shaft to turn freely. In order to synchronize the two winches, the bushing would have to be locked in place.
Figure SP-2-3: The bushing to be modified at the other end of the cranking shaft.
This image shows the old bushing and the new bushing next to each other.
Figure SP-2-4: Old bushing (left) and new bushing (right).
This image shows the test fit of the new coupler with the input/output shaft, held in place by a hairpin. The coupler is attached to the cranking shaft with a 3mm steel dowel.
Figure SP-2-5: Test fit of the shaft and the coupler before final assembly of the winches.

Middle Coupler

This image shows the mid-coupler of the lifting mechanism synchronization shaft in the retracted position. This will be the position during storage and while
Figure SP-2-6: Mid-coupler in retracted position (shafts not connected)
This image shows a CAD drawing of the mid-coupler in the connected position. Pins will be inserted through the two holes to lock the two shafts together
Figure SP-2-7: Mid-coupler with the sleeve in the extended position connecting both shafts.
This image shows the initial boring of the mid-coupler sleeve using a 3/4" annular cutter on the Jet 1340 lathe.
Figure SP-2-8: Boring out the mid-coupler sleeve on the lathe.

Connecting The Cable To The Crane

This image shows the temporary setup of the pulley mounting system. This photo was taken prior to the parts being completely welded together.
Figure SP-2-9: Pulley mount, for testing alignment. Not fully welded in this photo.
This image shows the bottom of the lifting bar where the shackle is attached and the winch cable hooks to the shackle. This picture was taken during the initial lifting test. Some components are just tacked in place, not fully welded.
Figure SP-2-10: Bottom of the lifting bar where the cable attaches.

We Have A Problem

This image shows the gantry crane assembled and raised to a height of ten feet. There is a problem with the left side winch, which makes it difficult to raise.
Figure SP-2-11: The gantry crane assembled and raised to a height of 10 feet.

Understanding The Problem

Alternative Methods

Thank You

Leave a Reply

Leave a Reply

Discover more from The Pretend Engineer

Subscribe now to keep reading and get access to the full archive.

Continue reading